Central Plant Phase I & Phase II
Central Plant Phase I & Phase II
Project Size
Phase I - East Campus Cooling Towers Replacement
Phase II - East and West Campus Chiller Replacement and East Campus Boiler Work
Project Budget
- Central Plant Phase I
- Contract: $1,099,370
- Final Cost: $1,088,563
- Central Plant Phase II
- Contract: $1,304,380
- Final Cost: $1,264,380
- Total Project Budget: $3,000,000
- Total Cost: $2,352,943
- Owner Allowance: $647,057
Project Timeline
Phase I | Date |
Board Award Contract | 04/12/16 |
Notice to Proceed - Begin Construction | 04/27/16 |
Complete Closeout | 09/22/16 |
Phase II | Date |
Board Award Contract | 08/09/16 |
Notice to Proceed | 09/01/16 |
Start Construction | 09/12/16 |
Complete Construction | 06/20/17 |
Contractor
Miller & Miller Mechanical Contracting Company, Inc
Page last updated January 4, 2019.