Workforce Development Center
Workforce Development Center
Project/Program Location
College Campus: Del Mar College’s West Campus located at Old Brownsville Rd., Corpus Christi, TX
Project Size
- Current Building Area: The new Space Program will be approximately 48,000 Gross Square Feet (GSF).
- GSF/USF: GSF includes both the Space Program noted below, as well as Unassignable Square Feet (USF) for service areas such as corridors, mechanical/electrical rooms, janitorial rooms, walls, partitions and chases.
Project Budget
- Base Bid: $12,600,000
- Alternate Bid Total: $702,000
- Total: $13,302,000
- Authorized Construction Budget Building/Sidewalks/Paving: $14,500,000
- Site & Utilities Extensions: $200,000
- Total Authorized Budget: $14,700,000
- Surplus: $1,398,000
Documents
Concept Design Approved by Board - April 12, 2016
Project Construction
- Space Program
- General: This Project will house the new Workforce Development Building.
- Preliminary Space Program: The preliminary space program will be provided to the Project Architect prior to fee/scope negotiations.
- New Building: Approximately 48,000 Gross Square Foot total
- Other Construction
- Sitework: Will address the current parking and general site renovations.
- Renovations to existing Sitework and improvements as needed.
- Demolition of existing Sitework and improvements as needed.
- Additional new sidewalks, paving, lighting and other site improvements. Additional new earth work,grading,and drainage about the Project Area.
- Campus Utility Systems: Modify service to building and connections to such as needed.
- Campus Drainage: Modify drainage of site as needed.
- Sitework: Will address the current parking and general site renovations.
- Landscaping: New Landscaping and Irrigation systems at yard/planting areas adjacent the new facilities.
Process | Date |
---|---|
Board Award Construction Contract | 03/21/17 |
Notice to Proceed - Begin Construction | 04/17/17 |
Complete Construction | Summer 2019 |
Complete Closeout | Summer 2019 |
Full Occupancy | Summer 2019 |
Project Architect
Turner | Ramirez Architects
General Contractor
Weaver & Jacobs Constructors
Construction Manager
AG|CM
Page last updated October 4, 2020.